1997 – Njord is finished at Stord

StS has followed the Njord A platform throughout the entire life cycle.

Njord A was the first EPC contract on the Norwegian continental shelf after Norsok was implemented in the mid 90’s. The contract was signed on April 1, 1995. The first steel plate was cut nine weeks later, and the rig left the yard August 7, 1997 – only 28 months later. Njord A started oil production 30 September the same year.

StS delivered scaffolding services and rigging services to Kværner during the construction, both at Stord and Verdal.